D
David F-H
I have set up a generic resource and used in a project but I find that the
assignments don't get published and so are not on the reporting database. I
would like them to be published as per normal resources, as I extract this
information from the reporting database for resource reporting. The only
other option I can see is using non-generic resources (but not allowing logon
to Project server) - but then you lose the "Match" function in "Build Team".
Are there any other options?
(FYI - using Project Server 2007).
assignments don't get published and so are not on the reporting database. I
would like them to be published as per normal resources, as I extract this
information from the reporting database for resource reporting. The only
other option I can see is using non-generic resources (but not allowing logon
to Project server) - but then you lose the "Match" function in "Build Team".
Are there any other options?
(FYI - using Project Server 2007).