Get graphical indicators to be displayed with colours In My Task v

M

Morten

In Project Server 2007 we have created an “enterprise field†on task level
that shows graphical indicators (Green, Yellow, Red light). The field is
displayed correctly in the project plan in Microsoft Project Professional and
ProjectCenter (ProjectDrillDown.aspx).

When we add the graphical indicator field to My Task view (mywork.aspx) the
colours are not show – the field is always blank. Any suggestions on how to
get the colours to be displayed in the task view?
 
M

Morten

The "My task uses a lower function grid (aka DHTML grid) - this eliminates
the need for ActiveX controls for most PWA users, however the grid is
somewhat graphically challenged - and therefore I can't display the lights.

Morten
 