P
pavel.gz
For single projects field TASK_UID (as well as ASSN_UID) is
MSP_WEB_ASSIGNMENTS table corresponds with the existing record in
MSP_TASKS.
However, when I publish master project (which has other projects
inserted), value of TASK_UID for these records becomes very big and
there is no record in MSP_TASKS that has such TASK_UID.
Is there any way I can get from this TASK_UID which project does
record in MSP_WEB_ASSIGNMENTS belongs to?
MSP_WEB_ASSIGNMENTS table corresponds with the existing record in
MSP_TASKS.
However, when I publish master project (which has other projects
inserted), value of TASK_UID for these records becomes very big and
there is no record in MSP_TASKS that has such TASK_UID.
Is there any way I can get from this TASK_UID which project does
record in MSP_WEB_ASSIGNMENTS belongs to?