T
texmaster
Hi
Hope everyone had a great Thanksgiving break
Got a question about formulas
I use 2 that calculate both working days left and a status light
Working Days Left: IIf([% Wor
Complete]=100,0,ProjDateDiff([Finish],Date(),[Project Calendar])
Status Light: IIf([% Complete]=100,"Blue",IIf(ProjDateDiff([Curren
Date],[Finish],[Project Calendar])/480<0,"Red",IIf(ProjDateDiff([Curren
Date],[Finish],[Projec
Calendar])/480<5,"Yellow",IIf(ProjDateDiff([Curren
Date],[Finish],[Project Calendar])/480>=5,"Green")))
The problem is when I open the projects back up like today, projec
doesn't compensate for the time lost aka the working days left and th
status light are still pulling from the original date I created th
spreadsheet and not recognizing the current date in computing eithe
formula
What am I doing wrong here
Hope everyone had a great Thanksgiving break
Got a question about formulas
I use 2 that calculate both working days left and a status light
Working Days Left: IIf([% Wor
Complete]=100,0,ProjDateDiff([Finish],Date(),[Project Calendar])
Status Light: IIf([% Complete]=100,"Blue",IIf(ProjDateDiff([Curren
Date],[Finish],[Project Calendar])/480<0,"Red",IIf(ProjDateDiff([Curren
Date],[Finish],[Projec
Calendar])/480<5,"Yellow",IIf(ProjDateDiff([Curren
Date],[Finish],[Project Calendar])/480>=5,"Green")))
The problem is when I open the projects back up like today, projec
doesn't compensate for the time lost aka the working days left and th
status light are still pulling from the original date I created th
spreadsheet and not recognizing the current date in computing eithe
formula
What am I doing wrong here