K
Ken
I think I'm a moderately skilled MSP user, but I'm a
little stuck on this one. At this site I'm on MSP2002
Standard.
Here's the situation: I have a task and I'd like to have
three people work on it together (yes, I could break it
into three tasks, one resource per, but follow me here).
No problem, except that I've plugged in availability data
(holidays, etc) into their calendars. Now MSP has one user
start work on one day, the second on another day and the
third on yet another day. I want to tell it "No!I want
them to work together, that if that delays the start of
the task, then that's what I want it to do" (but it
doesn't seem to hear me).
Ideas anyone? btw, my favourite view for working with
resource allocation is the task usage view (in the lower
half of a split window), and this clearly shows the
respective users' start dates. Have fun.
-Ken
little stuck on this one. At this site I'm on MSP2002
Standard.
Here's the situation: I have a task and I'd like to have
three people work on it together (yes, I could break it
into three tasks, one resource per, but follow me here).
No problem, except that I've plugged in availability data
(holidays, etc) into their calendars. Now MSP has one user
start work on one day, the second on another day and the
third on yet another day. I want to tell it "No!I want
them to work together, that if that delays the start of
the task, then that's what I want it to do" (but it
doesn't seem to hear me).
Ideas anyone? btw, my favourite view for working with
resource allocation is the task usage view (in the lower
half of a split window), and this clearly shows the
respective users' start dates. Have fun.
-Ken