M
Michelle Moulliet
I have several projects in my server with dependencies to other projects.
When I open some of them, the predecessor & successor tasks do not always
display the right date. I did a little investigation and found that for the
tasks that were not showing the right date, there were differences noted in
the project links dialog box in the predecessor & successor tabs.
I think I figured out how to fix the fact that updates are not being
automatically imported into the file & causing the differences notification.
I went to Tools>Options>View and deselected the Show Links Between Projects
Dialog on Open box & selected the Automatically Accept New External Data box.
This seemed to fix the situation so that I no longer see the dialog box and
the updates are automatically imported. Is this right? It seems like it's
working. Thanks for verifying for me.
When I open some of them, the predecessor & successor tasks do not always
display the right date. I did a little investigation and found that for the
tasks that were not showing the right date, there were differences noted in
the project links dialog box in the predecessor & successor tabs.
I think I figured out how to fix the fact that updates are not being
automatically imported into the file & causing the differences notification.
I went to Tools>Options>View and deselected the Show Links Between Projects
Dialog on Open box & selected the Automatically Accept New External Data box.
This seemed to fix the situation so that I no longer see the dialog box and
the updates are automatically imported. Is this right? It seems like it's
working. Thanks for verifying for me.