L
Lukey
Hi,
I wonder if anyone can help me with this little niggle? (Project 2007)
I have a project running which uses external dependencies ('ghos
tasks'). This is all working as expected. However, when I look at th
budget report, the ghost tasks appear in the table (not a problem i
itself) but worse than that, the cost associated with each of thes
ghost tasks is added to the total at the bottom!
This is quite frustrating as I make frequent use of this report and a
having to manually subtract the cost of all the ghost tasks from th
total to get the real figure. Does anyone know how I can prevent thi
from happening
I wonder if anyone can help me with this little niggle? (Project 2007)
I have a project running which uses external dependencies ('ghos
tasks'). This is all working as expected. However, when I look at th
budget report, the ghost tasks appear in the table (not a problem i
itself) but worse than that, the cost associated with each of thes
ghost tasks is added to the total at the bottom!
This is quite frustrating as I make frequent use of this report and a
having to manually subtract the cost of all the ghost tasks from th
total to get the real figure. Does anyone know how I can prevent thi
from happening