R
Riso
Hello everybody,
First of all thanks for this group and all contributions, this adds
tremendour value to each MSPS2003 admin.
I have one problem - our resource pool counts app. 450 resources. We
have to report their submitted hours 3 business days after the month
end. The trouble is that most of the resources actually fill in their
timesheets, however they forget to hit the "Update All" button to send
them to PMs for approval and the hours are missing.
I was wondering - is there a way at the server setup level to force the
"Update All" process either manually or automatically at certain time
of the month?
Thanks a lot for your answers,
Risiak...
First of all thanks for this group and all contributions, this adds
tremendour value to each MSPS2003 admin.
I have one problem - our resource pool counts app. 450 resources. We
have to report their submitted hours 3 business days after the month
end. The trouble is that most of the resources actually fill in their
timesheets, however they forget to hit the "Update All" button to send
them to PMs for approval and the hours are missing.
I was wondering - is there a way at the server setup level to force the
"Update All" process either manually or automatically at certain time
of the month?
Thanks a lot for your answers,
Risiak...