T
Trisha
I have a few users that appear to have messed with their calendars as it
seems to be isolated to their local copy of Project 2007.
MY COMPUTER: Tools --> Organizer --> Calendars --> 'Calendars Available =
Global(+non-cached Enterprise) I see:
24Hour-7DayWeek
FCBT-IT FTE Programmers
Intern Calendar
Standard
I see this in both columns.
However, on another users PC when I do the steps above I am seeing:
24Hour-7DayWeek
FCBT-IT FTE Programmers1
Intern Calendar
Standard11
Standard1
The standard is missing.
Is there a way to fix this persons settings? I would like to get these bogus
calendars out of there so we do not have further issues?
NOTE: I posted this on the Project group site and received not responses.
So, any input is greatly appreciated.
Thanks!
seems to be isolated to their local copy of Project 2007.
MY COMPUTER: Tools --> Organizer --> Calendars --> 'Calendars Available =
Global(+non-cached Enterprise) I see:
24Hour-7DayWeek
FCBT-IT FTE Programmers
Intern Calendar
Standard
I see this in both columns.
However, on another users PC when I do the steps above I am seeing:
24Hour-7DayWeek
FCBT-IT FTE Programmers1
Intern Calendar
Standard11
Standard1
The standard is missing.
Is there a way to fix this persons settings? I would like to get these bogus
calendars out of there so we do not have further issues?
NOTE: I posted this on the Project group site and received not responses.
So, any input is greatly appreciated.
Thanks!