Global Resource Calendar

R

Robert E Jones III

Am I correct in the fact that when a resource's calendar is updated in the
global resource pool it will also update any tasks they are assigned to in
projects.

Example lets say the resource is going to training the first week in
December and has 10 tasks on 2 projects that finish during this week. Will
the 2 project schedules reflect that these 10 tasks are now not going to be
delivered in the first week of December, but rather the seceond week of
December?
--
 
G

Gary L. Chefetz [MVP]

Robert:

The answer is yes, but know that the recalculation occurs the next time the
project is opened or another recalculation event occurs. Your PMs must then
publish the updated schedule before the scheduling changes are visible in
PWA.
 
R

Robert E Jones III

Thxs Gary I knew the answer just needed to show someone in the office its
just not my opinion....lol
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top