Hello,
My company are currently rolling out Project Professional with Project
Server bit by bit, so we’re only saving our plans to the server at the moment
and we’re not currently using the resourcing capability in the system.
We’ve switched off the email notification function, but when our project
managers enter resource into their plans, the dates on their plans are thrown
out if they choose a resource that has been used in another plan.
Is there anyway of switching off this resource leveling function at a global
level, so that 2 project managers can have the same resource on the same day
without the dates changing in their plans (as we’re currently using other
in-house software to deal with these conflicts at the moment).
Many thanks,
Kelly
My company are currently rolling out Project Professional with Project
Server bit by bit, so we’re only saving our plans to the server at the moment
and we’re not currently using the resourcing capability in the system.
We’ve switched off the email notification function, but when our project
managers enter resource into their plans, the dates on their plans are thrown
out if they choose a resource that has been used in another plan.
Is there anyway of switching off this resource leveling function at a global
level, so that 2 project managers can have the same resource on the same day
without the dates changing in their plans (as we’re currently using other
in-house software to deal with these conflicts at the moment).
Many thanks,
Kelly