I am using MS Project 2003 SP3.
I have blank tasks that show up in the resource usage view that do not show
up in the gantt view. In the resouce usage view the ID and Name fields are
blank, however the Start, Finish, and Work all have entries in them.
Are these quirks or human error?
I would like to delete them, unless someone can tell me they are serving
some useful purpose.
Thanks,
I have blank tasks that show up in the resource usage view that do not show
up in the gantt view. In the resouce usage view the ID and Name fields are
blank, however the Start, Finish, and Work all have entries in them.
Are these quirks or human error?
I would like to delete them, unless someone can tell me they are serving
some useful purpose.
Thanks,