C
Chris
Hello,
How can I change all tasks in a project from default to fixed duration?
This is what I did:
- select the whole task column
- select Project > task information
- select fixed duration in task type
The problem is, when I do this the blank lines in my project automatically
get a 1 day duration, and then I have to clean up all these lines.
Thanks.
How can I change all tasks in a project from default to fixed duration?
This is what I did:
- select the whole task column
- select Project > task information
- select fixed duration in task type
The problem is, when I do this the blank lines in my project automatically
get a 1 day duration, and then I have to clean up all these lines.
Thanks.