I
IloveEPM
Hi there,
for our program we have a global milestone list. These milestones are - so
far - available in a dedicated project plan. I would like to make these
milestones to be available in all project plans. The milestones shall also be
updated with changes as the name, finish date and % complete.
My idea was to insert the global milestone plan in each project - linked and
read only. This is OK for one plan. If I do it for a second plan, I get a
message that there might be errors publishing the plan (because it is already
inserted into another plan).
So my solution won't work. Has anyone an idea for another solution? We use
Project Server 2007.
Best regards
Michael
for our program we have a global milestone list. These milestones are - so
far - available in a dedicated project plan. I would like to make these
milestones to be available in all project plans. The milestones shall also be
updated with changes as the name, finish date and % complete.
My idea was to insert the global milestone plan in each project - linked and
read only. This is OK for one plan. If I do it for a second plan, I get a
message that there might be errors publishing the plan (because it is already
inserted into another plan).
So my solution won't work. Has anyone an idea for another solution? We use
Project Server 2007.
Best regards
Michael