Graphical report

W

Werner Hamann

Hi all

I have project 2007 server and want to make a graphical report for resource
usage.
That works so far. But as we have several projects a resource works on, we
want to see the result with the project names.
Is this possible?

Txs
Werner
 
B

Ben Howard

Two possible solutions.
1. Open the availability view within the resource centre for the selected
resource.
2. Use DataAnalysis to see each project and filter by the single resource.
 
W

Werner Hamann

Thanks Ben, but I think I did not ask properly.

The focus is on all resources (we only have 20, so no mass problem).
We want the resource usage for every resource and tasks like in Project view
resource:usage, but before every task the project, as a lot of tasks are
standard like design, analysis. So we do not know for which project we have
this effort if we don't have the project listed additional.
I'm afraid this is not possible because the excel pivot does not give me
this option.
Or do I find this report anywhere else?

Werner
 