D
Dave Coate
Hi all,
We are doing a test install of Project Server 2003. I have set up an
Administrative Project (based on Administrative Time template) to track
vacations etc and have entered some test data. Now I am trying to find a way
to graphically display the data on PWA for users. As a manager, whenever an
employee asks me for time off, my first question is: Is anyone else taking
time off at the time you are requesting? I am looking for a way in PWA for
the users to answer that question on their own.
The closest I can find is the Assignments Summary view for the project
on PWA. However, it does not display the data quite right. To give an
example: Resource A enters vacation for Feb 18 - Feb 22 while resource B
enters vacation from Feb 18 - Feb 26. Then when I go to the Assignments
Summary view in PWA, I see "Vacation" tasks for Resource A & B, but
graphically, both bars are identical. Both show the resource on "Vacation"
from Feb 18 - Feb 26. It seems to "add" over-lapping vacations together and
display the sum value for both resources.
Am I using the wrong view? Is there a better view to use? I have tried
all the views that are available as well as attempting to build a custom
view, but I cannot seem to get what I want.
The closest I have found to my goal is the "Task Usage" report in
Project Pro 2003. That gives me the data I want, but it is 1) not available
on PWA and 2) not graphical. I would accept a Task Usage report on PWA if
anyone can show me how to build one, but I would prefer graphical.
How do other people display this data to their users? I can't believe I
am the only person trying to do this.
Thanks,
Dave Coate, MCSE
We are doing a test install of Project Server 2003. I have set up an
Administrative Project (based on Administrative Time template) to track
vacations etc and have entered some test data. Now I am trying to find a way
to graphically display the data on PWA for users. As a manager, whenever an
employee asks me for time off, my first question is: Is anyone else taking
time off at the time you are requesting? I am looking for a way in PWA for
the users to answer that question on their own.
The closest I can find is the Assignments Summary view for the project
on PWA. However, it does not display the data quite right. To give an
example: Resource A enters vacation for Feb 18 - Feb 22 while resource B
enters vacation from Feb 18 - Feb 26. Then when I go to the Assignments
Summary view in PWA, I see "Vacation" tasks for Resource A & B, but
graphically, both bars are identical. Both show the resource on "Vacation"
from Feb 18 - Feb 26. It seems to "add" over-lapping vacations together and
display the sum value for both resources.
Am I using the wrong view? Is there a better view to use? I have tried
all the views that are available as well as attempting to build a custom
view, but I cannot seem to get what I want.
The closest I have found to my goal is the "Task Usage" report in
Project Pro 2003. That gives me the data I want, but it is 1) not available
on PWA and 2) not graphical. I would accept a Task Usage report on PWA if
anyone can show me how to build one, but I would prefer graphical.
How do other people display this data to their users? I can't believe I
am the only person trying to do this.
Thanks,
Dave Coate, MCSE