trawets
hi
I cant seem to find answer to my question so here goes
I would like to have groups of resources
ie
Engineers, welders etc, each group would have a max number eg 10 mech
engineers 10 elec engineers, 20 welders etc
when allocating resource rather than individuals I would like to
allocate a number from the total resource for that disciple
ie task A required 4 welder 2 mech I elec,
and then when leveling the resource we would level against the pool
total
its probably pretty simple but I'm not that experienced with MSP
any suggestion would be grateful
regards
trawets
I cant seem to find answer to my question so here goes
I would like to have groups of resources
ie
Engineers, welders etc, each group would have a max number eg 10 mech
engineers 10 elec engineers, 20 welders etc
when allocating resource rather than individuals I would like to
allocate a number from the total resource for that disciple
ie task A required 4 welder 2 mech I elec,
and then when leveling the resource we would level against the pool
total
its probably pretty simple but I'm not that experienced with MSP
any suggestion would be grateful
regards
trawets