B
bob.zoller
I have a Resource Usage view with two columns of interest: a "Resource
Name" column that contains resources and assignments, and a "Text1"
column that contains a project ID that was assigned in the Task Usage
view.
I would prefer to modify the view, or at worst make a report, that
allows me to show totals for each project for a resource. For example,
if a resource has 50 assignments in each of 2 projects, the default
Resource Usage view shows 100 rows for that resource, along with the
associated hours in weekly buckets. I would like to see only two rows
for that resource, one per project, with weekly hours for each
assignment in the project rolled up into a total for that project. I
might also want to add column "Text2" for project phase, and find a
view or report that shows subtotals by phase and by project, but at a
minimum I need a rollup by project. Any suggestions?
Thanks,
bzoller
Name" column that contains resources and assignments, and a "Text1"
column that contains a project ID that was assigned in the Task Usage
view.
I would prefer to modify the view, or at worst make a report, that
allows me to show totals for each project for a resource. For example,
if a resource has 50 assignments in each of 2 projects, the default
Resource Usage view shows 100 rows for that resource, along with the
associated hours in weekly buckets. I would like to see only two rows
for that resource, one per project, with weekly hours for each
assignment in the project rolled up into a total for that project. I
might also want to add column "Text2" for project phase, and find a
view or report that shows subtotals by phase and by project, but at a
minimum I need a rollup by project. Any suggestions?
Thanks,
bzoller