Grouping in View Resources Assignment

E

EasySite

In Resources View (View Resources Assignments) in PWA, I have grouped the
tasks by 'Project' and appears to be ordering in ascending order of Project.

Is there a way to make it so that it orders by the start date of projects?
This is so that I can see the list of tasks in order which they should be
worked on.

Thanks in advance
 
D

Dale Howard [MVP]

EasySite --

To apply Ascending sorting on your View Resource Assignments view, click the
Start column header until you see the gray up-pointing triangle to the left
of the word Start. Hope this helps.
 