R
R.Scott Fleming
I want to be able to find total labor hours per resource type, grouped by a
custom charge#(text1 field) that I assign manually to each task created (see
example shown below)…
I realize that I can find the grouped resources hours by using “Resource
Usage†but note that I can not group them by the charge#(text1 field)…
If I use the Task Usage view, I see that I can group by the charge# but then
can not group by the resource type….
Is this simply because the charge# field is not shared by the same tables?
What am I missing or not understanding…
Example:
Charge#
1-1-1 Contract review (Joe(1hr), Bob(1hr), Joyce(1hr))
1-1-1 Internal kick-off meeting (Mike(1hr), Bob (1hr), Sue (1hr))
2-1-1 Design phase1(Bob(40hrs), Sue(20hrs))
2-1-1 Design phase2 (Joe(8hrs), Bob (4hrs), Sue(2hrs))
2-1-2 Analysis phase1 (Sue(20hrs))
2-1-2 Analysis phase2 (Bob(20hrs), Sue(10hrs),Joyce(5hrs)
Desired grouping info by charge#, by labor resource:
1-1-1
Joe 1hr
Bob 2hrs
Joyce 1hr
Mike 1hr
Sue 1hr
2-1-1
Bob 44hrs
Sue 22hrs
Joe 8hrs
2-1-2
Sue 30hrs
Bob 20hrs
Joyce 5hrs
custom charge#(text1 field) that I assign manually to each task created (see
example shown below)…
I realize that I can find the grouped resources hours by using “Resource
Usage†but note that I can not group them by the charge#(text1 field)…
If I use the Task Usage view, I see that I can group by the charge# but then
can not group by the resource type….
Is this simply because the charge# field is not shared by the same tables?
What am I missing or not understanding…
Example:
Charge#
1-1-1 Contract review (Joe(1hr), Bob(1hr), Joyce(1hr))
1-1-1 Internal kick-off meeting (Mike(1hr), Bob (1hr), Sue (1hr))
2-1-1 Design phase1(Bob(40hrs), Sue(20hrs))
2-1-1 Design phase2 (Joe(8hrs), Bob (4hrs), Sue(2hrs))
2-1-2 Analysis phase1 (Sue(20hrs))
2-1-2 Analysis phase2 (Bob(20hrs), Sue(10hrs),Joyce(5hrs)
Desired grouping info by charge#, by labor resource:
1-1-1
Joe 1hr
Bob 2hrs
Joyce 1hr
Mike 1hr
Sue 1hr
2-1-1
Bob 44hrs
Sue 22hrs
Joe 8hrs
2-1-2
Sue 30hrs
Bob 20hrs
Joyce 5hrs