Grouping tasks using an Enterprise Outline Code in PjPro

F

Fabrizio

I have this problem: I want to group my tasks, inside the Gantt view, using
an enterprise outline code (lets call it EnterpriseWBS). If I insert this
field before the Task Name and apply the grouping, I can see the values for
EnterpriseWBS at project tasks level, but nothing is shown at the summary
grouping level.
This is different behaviour from both MSP2003 and PjPro2007 if I use a local
outline code instead of an enterprise code. In this case I can see a value
appear at the grouping summary level.
 