C
Chris
Hello,
I have a resource who has booked time to a job that they are not resourced
to. This task was not forseen, but is required.
Short of going through an involved process of creating the task, resourcing,
then getting the 'worker' to acknowledge and update their timesheet, can the
timesheet approver simple link the timesheet activity to a project?? And
have the task autopopulate itself into a porject?
Another example would be a manager who is not resourced to a project, but
has mentored a worker and wants to book his time to that job. When the
manager creates his timesheet that project is not on the automatic list, so
becomes an "unverified" line item. How can the timesheet approver apply that
time to the top level of that project - so as to capture the cost?
Thanks for the help
Chris
I have a resource who has booked time to a job that they are not resourced
to. This task was not forseen, but is required.
Short of going through an involved process of creating the task, resourcing,
then getting the 'worker' to acknowledge and update their timesheet, can the
timesheet approver simple link the timesheet activity to a project?? And
have the task autopopulate itself into a porject?
Another example would be a manager who is not resourced to a project, but
has mentored a worker and wants to book his time to that job. When the
manager creates his timesheet that project is not on the automatic list, so
becomes an "unverified" line item. How can the timesheet approver apply that
time to the top level of that project - so as to capture the cost?
Thanks for the help
Chris