H

P

Peo Sjoblom

Look in help for WORKDAY

WORKDAY(start_date,days,holidays)

it's part of the ATP add-in so if you didn't install it the first time you
need to install it,
tools>add-ins check ATP
 
J

JP

Thank you very much!!!!

Peo Sjoblom said:
Look in help for WORKDAY

WORKDAY(start_date,days,holidays)

it's part of the ATP add-in so if you didn't install it the first time you
need to install it,
tools>add-ins check ATP
 
J

JP

It is calculating correctly, however when I copy the formula, it is changing
the holiday field cells. Is there a way to lock in the Holiday field cells as
I originally used?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top