Hammock activities

K

Keith Cognevich

I remember in early versions of MS Project I could create a task and identify it as a "hammock". It was linked start-to-start with task A and finish-to-finish with task B. Because it was identified as a hammock, its duration was auto calculated as the time between the start of task A and the finish of task B. Any changes to task A or B (e.g., slippage) automatically changed start date, end date, and/or duration of the hammock. In other words, the hammock activity automatically lasted from the beginning of task A to the end of task B. I don't see that option anywhere in MS Project 2000 - how can I do it?
 
J

JackD

It is done the same way as before.
See the FAQ item 19, Hammock Tasks:

http://mvps.org/project/faqs.htm

-Jack

Keith Cognevich said:
I remember in early versions of MS Project I could create a task and
identify it as a "hammock". It was linked start-to-start with task A and
finish-to-finish with task B. Because it was identified as a hammock, its
duration was auto calculated as the time between the start of task A and the
finish of task B. Any changes to task A or B (e.g., slippage) automatically
changed start date, end date, and/or duration of the hammock. In other
words, the hammock activity automatically lasted from the beginning of task
A to the end of task B. I don't see that option anywhere in MS Project
2000 - how can I do it?
 
M

Mike Glen

Hi Keith,

Welcome to this Microsoft Project newsgroup :)

Please see FAQ Item: 19. Hammock Tasks.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 
K

Keith Cognevich

Thanks Jack and Mike. I obviously didn't look in the right place. It works, but it's different from what I remembered. I remembered establishing a hammock by how I defined the predecessors (ss and ff), not by linking the date fields. I've been away from Project for 5 years and things must have changed.
 
J

Jan De Messemaeker

Hi Keith

Haven't used Project before 1993, but since then definitely, no way to make
Hammock tasks by links. You probably remember an othe rproduct.
Greetings,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
Keith Cognevich said:
Thanks Jack and Mike. I obviously didn't look in the right place. It
works, but it's different from what I remembered. I remembered establishing
a hammock by how I defined the predecessors (ss and ff), not by linking the
date fields. I've been away from Project for 5 years and things must have
changed.
 
M

Michael Uyeda

Try looking at Microsoft Knowledge Base Article
141733, "How to Build a Hammock Task".
http://support.microsoft.com/default.aspx?scid=kb;en-
us;141733&Product=PRJ2K

I have not tried it yet, but I saw the article the other
day.
-----Original Message-----
I remember in early versions of MS Project I could create
a task and identify it as a "hammock". It was linked
start-to-start with task A and finish-to-finish with task
B. Because it was identified as a hammock, its duration
was auto calculated as the time between the start of task
A and the finish of task B. Any changes to task A or B
(e.g., slippage) automatically changed start date, end
date, and/or duration of the hammock. In other words, the
hammock activity automatically lasted from the beginning
of task A to the end of task B. I don't see that option
anywhere in MS Project 2000 - how can I do it?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top