Hammock Task FF + 3 Days?

S

ShawnMc

I have a series of tasks that run about 20 days at this point. I have a
documentation task that starts with the first task and runs 3 days past the
end of the last task. I know how to use the "paste link" function to create a
hammock task for my documentation task. Using this technique, I can make the
task start when the first task stats and end when the last task ends. How do
I tell project to let the documentation task end 3 days AFTER the last task
ends?
 