D
danimalx
Hi All,
I've read various tutorials on how to create a hammock task, and hav
tried doing so in the most simple fashion, but whenever I follow th
steps - and I'm certain they are correct - I end up with MSP refreshin
both dates to be the exact same date when I clearly have linked to th
first start and the last last date for the hammock task. I have n
predecessors and am not linking to summary dates. MSP refreshes th
dates a few times like it's in a calc loop or something, changing bot
the start and finish for the hammock task to the start, then change
both to the finish, then changes both back to the start. Any ideas??
Thanks,
Da
I've read various tutorials on how to create a hammock task, and hav
tried doing so in the most simple fashion, but whenever I follow th
steps - and I'm certain they are correct - I end up with MSP refreshin
both dates to be the exact same date when I clearly have linked to th
first start and the last last date for the hammock task. I have n
predecessors and am not linking to summary dates. MSP refreshes th
dates a few times like it's in a calc loop or something, changing bot
the start and finish for the hammock task to the start, then change
both to the finish, then changes both back to the start. Any ideas??
Thanks,
Da