Hi everyone,

Is there a way to retain the OLE links for a hammock task in an
Enterprise Template? The OLE links appear to be stripped out of the
template when a new project is created. Will we need to re-create the
hammock task for every new project created?

Thanks iin advance for your help.

milrock
 
D

Dale Howard [MVP]

milrock --

Microsoft Project does not allow OLE links in an enterprise project
template. Hope this helps.
 