J
Jesse
I just heard for the first time "hammock task" -- what's this? I think it
might be what I'm looking for.
I'm doing a large migration project that will require 75 applications to be
enhanced and tested. I want to have a task that is 10% of the total
time/effort to enhance and test the applications -- as an overage factor --
that changes as the time/effort changes. Would this requirement be satisfied
with a hammock task? How would I set this up for 10% of the duration? and
for 10% of the work effort?
might be what I'm looking for.
I'm doing a large migration project that will require 75 applications to be
enhanced and tested. I want to have a task that is 10% of the total
time/effort to enhance and test the applications -- as an overage factor --
that changes as the time/effort changes. Would this requirement be satisfied
with a hammock task? How would I set this up for 10% of the duration? and
for 10% of the work effort?