M
Martin M
Hi,
I am working with Ms Project 2003.
I have two questions regarding hammock task.
1/ I noticed when I create hammock task with dependency on the start and
finish date of a phase represented by a summary task (as describe in the
support process), the duration of the hammock task do not update when the
phase duration descrease.
So I have only create a dependency with the start date and the project
leader enters manually the duration.
Question : Is this reaction of Ms Project is normal ?
2/ When I use hammoc task as describe in 1/ the critical path does not
appear anymore either in Ms Project Pro and PWA. I suppose it is because I
have two critical path, the true one and the one with all the hammock task.
Am I correct ?
How to prevent this ?
Thanks for your answer.
Best regards
Martin
I am working with Ms Project 2003.
I have two questions regarding hammock task.
1/ I noticed when I create hammock task with dependency on the start and
finish date of a phase represented by a summary task (as describe in the
support process), the duration of the hammock task do not update when the
phase duration descrease.
So I have only create a dependency with the start date and the project
leader enters manually the duration.
Question : Is this reaction of Ms Project is normal ?
2/ When I use hammoc task as describe in 1/ the critical path does not
appear anymore either in Ms Project Pro and PWA. I suppose it is because I
have two critical path, the true one and the one with all the hammock task.
Am I correct ?
How to prevent this ?
Thanks for your answer.
Best regards
Martin