Hammock tasks in MPS 2003 and 2007

V

Victoria

Some of our Project Managers are using hammock tasks, however they are not
always being implemented properly. Is there a way to undo the link without
having to delete them in 2003?

Also, has their setup and use changed at all in MPS 2007?

thanks,
Victoria
 
G

Gérard Ducouret

Victoria,

How do they create the hammock tasks ? With Paste / Paste Special / Paste
Link ?
If so, you can undo the link with the sequence :
Edit / Links... / (select a link) Delete

Hope this helps,

Gérard Ducouret
 