I have 2 tasks that span the period of time between 2 fixed date milestones.
I want to be able to adjust one or both of the milestone dates and still have
the 2 tasks cover the intervening time.
task 1 14 days? Tue 11/15/05 Mon 12/5/05
task 2 14 days? Tue 11/15/05 Fri 12/2/05
mileston1 0 days Tue 11/15/05 Tue 11/15/05
mileston2 0 days Mon 12/5/05 Mon 12/5/05
The results above happened. Is there a particular sequence that should be
followed or steps to take to ensure consistant assignment of finish date?