Ted Bellinger
Using Project Professional 2003
I would like to be able to have an oversight task (like PM level of effort)
inherit the start date from the project start date and inherit te hend date
from th eproject end date.
I have seen a method for setting up hammock tasks in Project 2000. I have
tested using it in a draft project plan I am setting up now in PP2003 and it
seems to work ok, but I can't see the link definition after pasting the link
to the reference cell. I am concerned about my ability to troubleshoot
problems if I can't see the links. Is this recommended or not? Are there
better ways of having a task inherit the start and end dates of one or more
related/dependent tasks?
I would like to be able to have an oversight task (like PM level of effort)
inherit the start date from the project start date and inherit te hend date
from th eproject end date.
I have seen a method for setting up hammock tasks in Project 2000. I have
tested using it in a draft project plan I am setting up now in PP2003 and it
seems to work ok, but I can't see the link definition after pasting the link
to the reference cell. I am concerned about my ability to troubleshoot
problems if I can't see the links. Is this recommended or not? Are there
better ways of having a task inherit the start and end dates of one or more
related/dependent tasks?