K
kinetix
I'm working on a complex design/build construction project that require
owner review of multiple design packages prior to start of construction
The entire construction schedule is dependent on their review an
authorization to proceed. The original schedule included time for tha
review, but they are falling behind and can't/won't provide a projecte
remaining duration or completion date. Once they have completed thei
review, I can update the actual finish dates, but until that point
need a clean way to insert delays to to keep the rest of the schedul
from just slipping into the past. The best way I've come up with is t
use the leveling delay which then zeros out when I enter actual dates
Any ideas. thank
owner review of multiple design packages prior to start of construction
The entire construction schedule is dependent on their review an
authorization to proceed. The original schedule included time for tha
review, but they are falling behind and can't/won't provide a projecte
remaining duration or completion date. Once they have completed thei
review, I can update the actual finish dates, but until that point
need a clean way to insert delays to to keep the rest of the schedul
from just slipping into the past. The best way I've come up with is t
use the leveling delay which then zeros out when I enter actual dates
Any ideas. thank