D
David R
When your boss puts "TBA" for [start] or [duration] how is the best
way to handle this? He wants it printed in a gantt chart.
way to handle this? He wants it printed in a gantt chart.
John Beamish said:<mounting soap box>
Technically, except for kickoff tasks, the task start date is always "tba"
because it is derived from the completion date (and lags, if necessary) of
the predecessor task or tasks. Entering a start date (except in certain
circumstances) curtails the built-in functionality of Project to
automatically push out (or pull in) dependant dates if predecessor tasks are
running late or early.
<dismounting from soap box>
Format | Bar styles ... and click on the Task item in the upper portion of
the display and then click on the Text tab in the lower portion. Default
(at least on my machine) is to display the resources to the right of the
Gantt bar. You could replace that with the Duration field. In P2003 (I'm
not certain which release it appears in) you get a question mark along with
the duration if it is only estimated.
As for the Start dates (and you can also do this for the durations), you
could do something the same way. Instead of changing the bar text to
display the Duration (as you did in the paragraph above), you could change
it to display the contents of the Text1 field. In the grid portion of the
Gantt view display the Text1 field and, for the affected tasks, enter
something like "Est." or "TBA". That notation will appear on the bar chart
portion of the Gantt view.
David R said:When your boss puts "TBA" for [start] or [duration] how is the best
way to handle this? He wants it printed in a gantt chart.
Gérard Ducouret said:Hello David, hello John,
Could you explain to a French guy what the acronym TBA stands for?
Thanks,
Gérard
John Beamish said:<mounting soap box>
Technically, except for kickoff tasks, the task start date is always "tba"
because it is derived from the completion date (and lags, if necessary) of
the predecessor task or tasks. Entering a start date (except in certain
circumstances) curtails the built-in functionality of Project to
automatically push out (or pull in) dependant dates if predecessor tasks are
running late or early.
<dismounting from soap box>
Format | Bar styles ... and click on the Task item in the upper portion of
the display and then click on the Text tab in the lower portion. Default
(at least on my machine) is to display the resources to the right of the
Gantt bar. You could replace that with the Duration field. In P2003 (I'm
not certain which release it appears in) you get a question mark along with
the duration if it is only estimated.
As for the Start dates (and you can also do this for the durations), you
could do something the same way. Instead of changing the bar text to
display the Duration (as you did in the paragraph above), you could change
it to display the contents of the Text1 field. In the grid portion of the
Gantt view display the Text1 field and, for the affected tasks, enter
something like "Est." or "TBA". That notation will appear on the bar chart
portion of the Gantt view.
David R said:When your boss puts "TBA" for [start] or [duration] how is the best
way to handle this? He wants it printed in a gantt chart.
SSF said:To Be Announced; sort of the same as To Be Determined (TBD) or To Be
Confirmed (TBC).
DJM
necessary)Gérard Ducouret said:Hello David, hello John,
Could you explain to a French guy what the acronym TBA stands for?
Thanks,
Gérardportionof tasks
areofthe display and then click on the Text tab in the lower portion. Default
(at least on my machine) is to display the resources to the right of the
Gantt bar. You could replace that with the Duration field. In P2003 (I'm
not certain which release it appears in) you get a question mark along with
the duration if it is only estimated.
As for the Start dates (and you can also do this for the durations), you
could do something the same way. Instead of changing the bar text to
display the Duration (as you did in the paragraph above), you could change
it to display the contents of the Text1 field. In the grid portion of the
Gantt view display the Text1 field and, for the affected tasks, enter
something like "Est." or "TBA". That notation will appear on the bar chart
portion of the Gantt view.
When your boss puts "TBA" for [start] or [duration] how is the best
way to handle this? He wants it printed in a gantt chart.
Gérard Ducouret said:Hello David, hello John,
Could you explain to a French guy what the acronym TBA stands for?
Thanks,
Gérard
John Beamish said:<mounting soap box>
Technically, except for kickoff tasks, the task start date is always "tba"
because it is derived from the completion date (and lags, if necessary) of
the predecessor task or tasks. Entering a start date (except in certain
circumstances) curtails the built-in functionality of Project to
automatically push out (or pull in) dependant dates if predecessor tasks are
running late or early.
<dismounting from soap box>
Format | Bar styles ... and click on the Task item in the upper portion of
the display and then click on the Text tab in the lower portion. Default
(at least on my machine) is to display the resources to the right of the
Gantt bar. You could replace that with the Duration field. In P2003 (I'm
not certain which release it appears in) you get a question mark along with
the duration if it is only estimated.
As for the Start dates (and you can also do this for the durations), you
could do something the same way. Instead of changing the bar text to
display the Duration (as you did in the paragraph above), you could change
it to display the contents of the Text1 field. In the grid portion of the
Gantt view display the Text1 field and, for the affected tasks, enter
something like "Est." or "TBA". That notation will appear on the bar chart
portion of the Gantt view.
David R said:When your boss puts "TBA" for [start] or [duration] how is the best
way to handle this? He wants it printed in a gantt chart.
-----Original Message-----
Hello David, hello John,
Could you explain to a French guy what the acronym TBA stands for?
Thanks,
Gérard
"John Beamish" <JLBeamishAThotmailDOTcom> a écrit dans le message de
predecessor tasks<mounting soap box>
Technically, except for kickoff tasks, the task start date is always "tba"
because it is derived from the completion date (and lags, if necessary) of
the predecessor task or tasks. Entering a start date (except in certain
circumstances) curtails the built-in functionality of Project to
automatically push out (or pull in) dependant dates if
arequestion mark alongrunning late or early.
<dismounting from soap box>
Format | Bar styles ... and click on the Task item in the upper portion of
the display and then click on the Text tab in the lower portion. Default
(at least on my machine) is to display the resources to the right of the
Gantt bar. You could replace that with the Duration field. In P2003 (I'm
not certain which release it appears in) you get a
withappear on the barthe duration if it is only estimated.
As for the Start dates (and you can also do this for the durations), you
could do something the same way. Instead of changing the bar text to
display the Duration (as you did in the paragraph above), you could change
it to display the contents of the Text1 field. In the grid portion of the
Gantt view display the Text1 field and, for the affected tasks, enter
something like "Est." or "TBA". That notation will
chartportion of the Gantt view.
chart.David R said:When your boss puts "TBA" for [start] or [duration] how is the best
way to handle this? He wants it printed in a gantt
.
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.