H
Hannu Koivisto
Greetings,
I'm experimenting with MSP's tracking features and faced a problem
I haven't been able to find a solution for (I've been reading a
book about MSP, online help, 30 pages of Google results from this
group, <http://project.mvps.org/faqs.htm> and some articles in
web).
Suppose I have a task whose baseline start was estimated/scheduled
to be 2006-09-19, finish 2006-09-26 and only 7.5h of actual work,
resulting to 17% units given the used calendar. Task is of type
Fixed Units mainly because that works the best for me while I
fiddle with the initial plan.
I now know that the task was started and finished as scheduled but
14.5h of actual work was done. I haven't entered any
tracking/actual information this far. I select Task Sheet view and
Tracking table, which seems to contain all the information I need
to enter.
If I set actual start and actual finish dates, MSP calculates
actual work to be 1 day (7.5h), which is expected. But now I need
to correct that and I cannot figure out how. If I try to modify
actual work to be 14.5h, MSP adjusts the actual finish date later.
I have tried to disable automatic calculation via Tools -> Options
-> Calculation, change task type, enter real actual hours and %
comp. to 100% before setting actual finish date but no matter what
I do, MSP insists on keeping the units intact and updating either
actual finish or actual work when I update the other.
That is, if I have set actual start and actual finish, I would like
it to update actual units according to actual work. How would I
accomplish that?
I'm experimenting with MSP's tracking features and faced a problem
I haven't been able to find a solution for (I've been reading a
book about MSP, online help, 30 pages of Google results from this
group, <http://project.mvps.org/faqs.htm> and some articles in
web).
Suppose I have a task whose baseline start was estimated/scheduled
to be 2006-09-19, finish 2006-09-26 and only 7.5h of actual work,
resulting to 17% units given the used calendar. Task is of type
Fixed Units mainly because that works the best for me while I
fiddle with the initial plan.
I now know that the task was started and finished as scheduled but
14.5h of actual work was done. I haven't entered any
tracking/actual information this far. I select Task Sheet view and
Tracking table, which seems to contain all the information I need
to enter.
If I set actual start and actual finish dates, MSP calculates
actual work to be 1 day (7.5h), which is expected. But now I need
to correct that and I cannot figure out how. If I try to modify
actual work to be 14.5h, MSP adjusts the actual finish date later.
I have tried to disable automatic calculation via Tools -> Options
-> Calculation, change task type, enter real actual hours and %
comp. to 100% before setting actual finish date but no matter what
I do, MSP insists on keeping the units intact and updating either
actual finish or actual work when I update the other.
That is, if I have set actual start and actual finish, I would like
it to update actual units according to actual work. How would I
accomplish that?