Hello koolkat,
My comments are inline below.
Julie
koolkat said:
ok I've discovered something...I can repeat this issue now.
Follow these steps to repeat
1) Start New Project
[Julie] Done. Project start date set to 12/10/09. Using calendar,
"Standard" with no motifications.
2) Set Level to Manual
3) Create Task 1 Resource "a", Date 12/10/09 to 12/19/09, priority
600
[Julie] 12/19 is a Sunday. What calendar are you using?
4) Create Task 2 Resource "a", Date 12/14/09 to 12/15/09, priority
500
[Julie] I am guessing you typed in a start date to force the task to
start on 12/14?
5) Create Task 3 can be anything non-related
[Julie] and Assign resource A?
6) Delete Task 3
7) Now Manual Level
At this point my Task 2 does not move to after Task 1 as it should
until I
Manual Level again. This seems to only occur after a deletion.
Is this a
known bug?
[Julie] Sorry, I can't reproduce. When I choose Level Now, task 2
moves very nicely without the need to repeat. What other settings
in the Resource Leveling command do you have selected? What version
(including service pack) do you have installed?