B
Bill
Hi, I have a large excel data worksheet which has this
basic look:
Item: PointA PointB PointC PointD PointE
#01 01-Feb 04-Feb 05-Feb 13-Feb 22-Feb
#02 03-Feb 06-Feb 10-Feb 15-Feb 27-Feb
#03 03-Feb 15-Feb 19-Feb 01-Mar 10-Mar
#04 15-Feb 22-Feb 28-Feb 01-Mar 12-Mar
#05 20-Feb 22-Feb 28-Feb 03-Mar 06-Mar
#06 24-Feb 28-Feb 11-Mar 12-Mar 14-Mar
#07 11-Mar 14-Mar 16-Mar 17-Mar 22-Mar
Its much larger.. (700 rows/25 columns) but this gives a
picture: I have been trying to figure out a way
(Formuals) to evaluate the AVERAGE time in Days between
Points (by month..and in days) and place the results on
another worksheet. I am doing this manually... but there
has to be a better way (and faster) Currently I am
manually calculating the days between points for each
item. Then sorting point "A" for all of Feb and then
calculating the Average for Feb - March Etc. so I can
say for example:
In January-02 the Average time it took for (insert the
number of time Jan-02 appeared in Column B) an
average of 5.8 days as compared to June-03 we had the
volume (insert the number of times Jun-02 appears in
Column B) an average of 10.4 days .. to get from point A
to point B
Thanks for your help
basic look:
Item: PointA PointB PointC PointD PointE
#01 01-Feb 04-Feb 05-Feb 13-Feb 22-Feb
#02 03-Feb 06-Feb 10-Feb 15-Feb 27-Feb
#03 03-Feb 15-Feb 19-Feb 01-Mar 10-Mar
#04 15-Feb 22-Feb 28-Feb 01-Mar 12-Mar
#05 20-Feb 22-Feb 28-Feb 03-Mar 06-Mar
#06 24-Feb 28-Feb 11-Mar 12-Mar 14-Mar
#07 11-Mar 14-Mar 16-Mar 17-Mar 22-Mar
Its much larger.. (700 rows/25 columns) but this gives a
picture: I have been trying to figure out a way
(Formuals) to evaluate the AVERAGE time in Days between
Points (by month..and in days) and place the results on
another worksheet. I am doing this manually... but there
has to be a better way (and faster) Currently I am
manually calculating the days between points for each
item. Then sorting point "A" for all of Feb and then
calculating the Average for Feb - March Etc. so I can
say for example:
In January-02 the Average time it took for (insert the
number of time Jan-02 appeared in Column B) an
average of 5.8 days as compared to June-03 we had the
volume (insert the number of times Jun-02 appears in
Column B) an average of 10.4 days .. to get from point A
to point B
Thanks for your help