E
EPMLearner
Hi,
Just wanted someone to please tell me if I am right or wrong. I am pretty
well versed in Microsoft Project but this is driving me batty. We have
users in our environment that are using "Change Working Time" to zero out
hours for a resource is not working on a task for a particular day (even if
they are not on vacation). The plans that they work on are always messed up
because of bad practices and I find that most are rigging plans to get them
to work. It is truly driving me crazy because they level almost on a
daily/weekly basis (don't ask - that is another pet-peeve altogether). The
problem I have identified is this - If they ever decide to go back and
schedule that resource during the timeframe they have them blocked for...they
can't unless they Change Working time and then they have leveled so much that
I can't even explain what happened up to that point. It impacts how the
system levels because of course it avoids those dates, thus it possibly
pushes the project out further and furthermore, if we begin to put these
projects on EPM they will mess up the resource availabilty for other projects
by doing this.
If I am wrong, will someone please correct me. Or could someone give me a
better approach/explaination to get them to stop this.
Just wanted someone to please tell me if I am right or wrong. I am pretty
well versed in Microsoft Project but this is driving me batty. We have
users in our environment that are using "Change Working Time" to zero out
hours for a resource is not working on a task for a particular day (even if
they are not on vacation). The plans that they work on are always messed up
because of bad practices and I find that most are rigging plans to get them
to work. It is truly driving me crazy because they level almost on a
daily/weekly basis (don't ask - that is another pet-peeve altogether). The
problem I have identified is this - If they ever decide to go back and
schedule that resource during the timeframe they have them blocked for...they
can't unless they Change Working time and then they have leveled so much that
I can't even explain what happened up to that point. It impacts how the
system levels because of course it avoids those dates, thus it possibly
pushes the project out further and furthermore, if we begin to put these
projects on EPM they will mess up the resource availabilty for other projects
by doing this.
If I am wrong, will someone please correct me. Or could someone give me a
better approach/explaination to get them to stop this.