HELP... (groups/teams)

D

Dale Howard [MVP]

mdoster --

Andrew Lavinsky already answered your question. To emphasize what he told
you, there is no direct way to accomplish what you want to do, which is to
assign a team of resources to a task. Hope this helps.
 
J

JulieS

Hi mdoster,

Andrew's post is correct. You wrote:
-------------------------
Ah, well... that explains it. I'm not running Project Server -
but desktop...So, there still has to be a way in Desktop to
accomplish the same thing, so perhaps one of you can help me.. I
have a bunch of individuals (resources) that serve on various
teams that work together (at the same time) on a project. I want
to be able to list the team name and have it take the
individual resource schedules into consideration... Does that
make sense? I've tried the group feature, but I can't see that
it does what I need. Or it could just be that I'm an idiot and
don't understand how to make it work.
----------------------------

Project does not have the capability to pick resources from a
group or a team.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 