Hi all - especially Dale + Gary !!
Ive got a bit of a problem and hope you can help
We are using Project + PWA 2003 with lock down actuals and have now got 2
types of plans - one set for high level timesheet tasks and one set of low
level plans.
The low level plans have only generic resources assigned to detailed
tasks.....
The problem we are geeting is the out of sync message - which if we ignore
is ok but if we do sync it kills all the tasks progress back to 0%. - this
does not make sense to me as publishing cannot occur as generics do not
generate timesheets - its doing my head in now - is it a known bug ?
we are running project 2003 with SP1
Thanks in advance
Mat
Ive got a bit of a problem and hope you can help
We are using Project + PWA 2003 with lock down actuals and have now got 2
types of plans - one set for high level timesheet tasks and one set of low
level plans.
The low level plans have only generic resources assigned to detailed
tasks.....
The problem we are geeting is the out of sync message - which if we ignore
is ok but if we do sync it kills all the tasks progress back to 0%. - this
does not make sense to me as publishing cannot occur as generics do not
generate timesheets - its doing my head in now - is it a known bug ?
we are running project 2003 with SP1
Thanks in advance
Mat