help needed w/ workday formula

V

vennesa

I am using the workday formula: =WORKDAY(start_date, days, holidays)
But it's not calculating the holiday list for some reason - and it's
NOT throwing me an error. It's just not calculating the list.

My holiday list is referenced as H7:H17

So the formula I have plugged in is: =WORKDAY(E8,5,H7:H17)

It doesn't calculate the weekends (which is good) - but it completely
neglects the holiday range.
Any ideas?

All help is greatly appreciated!
Thanks,
Vennesa
 