D
dm0502
Our IT department has 8 employees that plan and schedule projects. We have
just started using Project Pro and Project Server recently, and could use
some advice.
The goals are:
- To be able to see what projects are scheduled and when projects are needed
and/or projected to be complete
- A way to manage resource allocations for the 22 employees in our
department (all of which have other work outside the projects to which they
are assigned)
- Tracking project time accurately so that we can use these project plans as
templates for future similar projects
Because we are all very busy with other work, we tried to set up Project and
Project Server as simply as possible. Also, because we need to review
everyone’s projects together, we tried to have everyone use the same task
types.
Currently, we use fixed work for each project. Project managers input the
tasks that need to be completed, determine dependencies, input an estimate of
the amount of work that is needed for each task, and assign resources. Our
resources’ availability percents have been adjusted to reflect how much time
they actually can work on projects (anywhere from 10% up to about 75%).
If a project has a drop dead deadline and the schedule does not fit into the
time line, we adjust the resource allocations where we can to try to get the
work completed in the timeframe, or determine which tasks can be scaled back.
Resources use PWA to update the time worked on tasks, and time remaining if
needed.
This mostly works for us, except, it takes an incredible amount of time to
manage, especially as tasks slip and dates change. Some of us have 5 or 6 or
more projects underway at the same time. To some, it feels as if we are
‘playing’ around with the project, to get it to ‘work’ into a pre-determined
schedule.
Is there anything else we should be doing, or can do, to make this any
simpler for us? One manager wants to use fixed duration to set the start and
finish dates for each task, so that even if work runs behind schedule, or
more is added, the project still shows the date that tasks need to complete.
This does not seem like it is managing the reality of a project, it’s only a
way to make sure your dates always look right.
Any advice?
Thanks in advance.
just started using Project Pro and Project Server recently, and could use
some advice.
The goals are:
- To be able to see what projects are scheduled and when projects are needed
and/or projected to be complete
- A way to manage resource allocations for the 22 employees in our
department (all of which have other work outside the projects to which they
are assigned)
- Tracking project time accurately so that we can use these project plans as
templates for future similar projects
Because we are all very busy with other work, we tried to set up Project and
Project Server as simply as possible. Also, because we need to review
everyone’s projects together, we tried to have everyone use the same task
types.
Currently, we use fixed work for each project. Project managers input the
tasks that need to be completed, determine dependencies, input an estimate of
the amount of work that is needed for each task, and assign resources. Our
resources’ availability percents have been adjusted to reflect how much time
they actually can work on projects (anywhere from 10% up to about 75%).
If a project has a drop dead deadline and the schedule does not fit into the
time line, we adjust the resource allocations where we can to try to get the
work completed in the timeframe, or determine which tasks can be scaled back.
Resources use PWA to update the time worked on tasks, and time remaining if
needed.
This mostly works for us, except, it takes an incredible amount of time to
manage, especially as tasks slip and dates change. Some of us have 5 or 6 or
more projects underway at the same time. To some, it feels as if we are
‘playing’ around with the project, to get it to ‘work’ into a pre-determined
schedule.
Is there anything else we should be doing, or can do, to make this any
simpler for us? One manager wants to use fixed duration to set the start and
finish dates for each task, so that even if work runs behind schedule, or
more is added, the project still shows the date that tasks need to complete.
This does not seem like it is managing the reality of a project, it’s only a
way to make sure your dates always look right.
Any advice?
Thanks in advance.