M
Marc T
Hi All,
I have the following formula to show progress of an item at a particular date:
=IF($D329<>"",IF($D329<=V$3,($D$341/100)*$S329),0)+IF($E329<>"",IF($E329<=V$3,($E$341/100)*$S329),0)+IF($F329<>"",IF($F329<=V$3,($F$341/100)*$S329),0)+IF($G329<>"",IF($G329<=V$3,($G$341/100)*$S329),0)+IF($H329<>"",IF($H329<=V$3,($H$341/100)*$S329),0)+IF($I329<>"",IF($I329<=V$3,($I$341/100)*$S329),0)+IF($J329<>"",IF($J329<=V$3,($J$341/100)*$S329),0)+IF($K329<>"",IF($K329<=V$3,($K$341/100)*$S329),0)
V3 is the current date, S329 is the budgeted hours, D329:K329 are
deliverable dates, and D341:K341 are progress percentages...
Basically it's adding the values in the progress percentages in D341341 if
the corresponding date with D329:K329 is before the date in V3 and then
multiplying by the budget figure.
Is there any obvious way to simplify? Maybe an array formula?
Cheers as ever!
Marc
I have the following formula to show progress of an item at a particular date:
=IF($D329<>"",IF($D329<=V$3,($D$341/100)*$S329),0)+IF($E329<>"",IF($E329<=V$3,($E$341/100)*$S329),0)+IF($F329<>"",IF($F329<=V$3,($F$341/100)*$S329),0)+IF($G329<>"",IF($G329<=V$3,($G$341/100)*$S329),0)+IF($H329<>"",IF($H329<=V$3,($H$341/100)*$S329),0)+IF($I329<>"",IF($I329<=V$3,($I$341/100)*$S329),0)+IF($J329<>"",IF($J329<=V$3,($J$341/100)*$S329),0)+IF($K329<>"",IF($K329<=V$3,($K$341/100)*$S329),0)
V3 is the current date, S329 is the budgeted hours, D329:K329 are
deliverable dates, and D341:K341 are progress percentages...
Basically it's adding the values in the progress percentages in D341341 if
the corresponding date with D329:K329 is before the date in V3 and then
multiplying by the budget figure.
Is there any obvious way to simplify? Maybe an array formula?
Cheers as ever!
Marc