K
Kathleen
Hi Everyone - I am using MSP 2003. I am currently running in a mixed
enviornment (PM selects which task tracking method to utilize- acutal or %
complete) We also allow the PM to push out the published fields of Actual
Start, Actual Finish and Baseline work by project.
My issue is that the timesheet view may show % Work Complete column for one
resource, but the next resource may not show that column in their Tasks view.
Has anyone ever seen this? It seems to get resolved if I go into the
timesheet view (manage views) and click Save Changes; however, I'm concerned
there is a bigger issue going on here.
Are the columns that appear in the timesheet view updated by the OLAP cube?
I have noticed that my OLAP cube update on an overnight auto update takes 5
minutes and if I manually update it takes about 12 minutes.
THANKS FOR ANY HELP YOU CAN PROVIDE.
Kathleen, PMP
enviornment (PM selects which task tracking method to utilize- acutal or %
complete) We also allow the PM to push out the published fields of Actual
Start, Actual Finish and Baseline work by project.
My issue is that the timesheet view may show % Work Complete column for one
resource, but the next resource may not show that column in their Tasks view.
Has anyone ever seen this? It seems to get resolved if I go into the
timesheet view (manage views) and click Save Changes; however, I'm concerned
there is a bigger issue going on here.
Are the columns that appear in the timesheet view updated by the OLAP cube?
I have noticed that my OLAP cube update on an overnight auto update takes 5
minutes and if I manually update it takes about 12 minutes.
THANKS FOR ANY HELP YOU CAN PROVIDE.
Kathleen, PMP