J
jtorresparodi
I will really appreciate some help on this.
At the company I work for (software development company), Project
Managers (PM) are using MSP to calculate the project cost as well as
to manage the project. In fact, rather than calculating the cost they
are calculating how much to charge the client (price).
It´s very common to charge the client for an Analyst during the whole
project duration, even though the Analyst does not have tasks assigned
for the whole duration of the project. This is because the analyst is
always performing, at least, support activities.
In order to calculate the "price", PM assign the Analyst to the
summary tasks. This works fine to calculate the price. However, it
doesn't allow to calculate the SPI right. Also it doesn't allow to
calculate resource usage. (if the resource has an specific task
assigned to him, it will show up as resource overuse).
Can you advise me on this? I´ve tried with hammock tasks for the
support activities for a given resource. I was able to solve the SPI
issue but I still get resource overuse when the same resource is
assigned to specific tasks.
Thank you for your help.
At the company I work for (software development company), Project
Managers (PM) are using MSP to calculate the project cost as well as
to manage the project. In fact, rather than calculating the cost they
are calculating how much to charge the client (price).
It´s very common to charge the client for an Analyst during the whole
project duration, even though the Analyst does not have tasks assigned
for the whole duration of the project. This is because the analyst is
always performing, at least, support activities.
In order to calculate the "price", PM assign the Analyst to the
summary tasks. This works fine to calculate the price. However, it
doesn't allow to calculate the SPI right. Also it doesn't allow to
calculate resource usage. (if the resource has an specific task
assigned to him, it will show up as resource overuse).
Can you advise me on this? I´ve tried with hammock tasks for the
support activities for a given resource. I was able to solve the SPI
issue but I still get resource overuse when the same resource is
assigned to specific tasks.
Thank you for your help.