D
Dgreen419
Good Morning
I am using the Workday function to calculate working days from
particular date. Currently I have =WORKDAY(H3,11,0) as my calculation.
want the workday function to look at multiple dates in multiple cells
Is that possible?
Currently my H3 date is 05/09/2012 and my 11 day work day date in cel
E3 is 05/24/2012. I want to see the E3 cell reflect my new workdate if
was to enter a new date in cell I3, J3, K3 and so on.
Any help would be appreciated! Thanks!
--Dgree
I am using the Workday function to calculate working days from
particular date. Currently I have =WORKDAY(H3,11,0) as my calculation.
want the workday function to look at multiple dates in multiple cells
Is that possible?
Currently my H3 date is 05/09/2012 and my 11 day work day date in cel
E3 is 05/24/2012. I want to see the E3 cell reflect my new workdate if
was to enter a new date in cell I3, J3, K3 and so on.
Any help would be appreciated! Thanks!
--Dgree