When I use the Resource Usage View, and run the Analyze TimeScale Data In
Excel feature, it shows a summary (one line total, byt time period)) for the
resource.

Is there anyway that I can get the task level detail on the export? For
example, if Joe worked on three tasks, I'd like to see those tasks appear on
the Excel export as well as the summary line..

Thanks.
 
J

John

PM Training 12 said:
When I use the Resource Usage View, and run the Analyze TimeScale Data In
Excel feature, it shows a summary (one line total, byt time period)) for the
resource.

Is there anyway that I can get the task level detail on the export? For
example, if Joe worked on three tasks, I'd like to see those tasks appear on
the Excel export as well as the summary line..

Thanks.

PM Training,
With the Analyze Timsecale data in Excel utility? Not easily. You could
try multiple exports (e.g. from the Resource Usage view and the Task
Usage view) and then combine the data once it is in Excel but it would
probably be easier to simply copy and paste the Usage view data.

The utility was designed to be functional but in a rather generic way.
The details just weren't built in. If you have VBA experience you could
modify the code for the utility yourself to include the details but in
my opinion a much better approach is to create your own custom VBA macro
to export and format whatever data you want, or, have someone develop
the code for you.

John
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top