D
Dab
I'm trying to create an excel sheet that adds a number of segment duration
times together to provide the total time for all segments. No problem.
Then I calculate the start time and end time for each of the segments. The
start time is calculated using the end time of the previous segment. The
end time is calculated by added the segment time to the start time. No
problem
But... When I cut and insert a row cells containing the segment start, end,
and duration time, the sheet gets all screwed up as the relative cell
reference are adjusted for the newly inserted line, and I don't want them to
be. I can't use an absolute reference, or I end up with the same cut and
paste problem
Is there a way to turn off how a relative cell reference changes when you
move the cell?
For instance, I want a cell to be equal to the cell above. If I move the
first cell, I want it to be equal to the cell above, in it's new location,
not the old one. I thought that there was a referencing mode for this but I
can't find any information on it.
Thanks for any advice.
Dab
times together to provide the total time for all segments. No problem.
Then I calculate the start time and end time for each of the segments. The
start time is calculated using the end time of the previous segment. The
end time is calculated by added the segment time to the start time. No
problem
But... When I cut and insert a row cells containing the segment start, end,
and duration time, the sheet gets all screwed up as the relative cell
reference are adjusted for the newly inserted line, and I don't want them to
be. I can't use an absolute reference, or I end up with the same cut and
paste problem
Is there a way to turn off how a relative cell reference changes when you
move the cell?
For instance, I want a cell to be equal to the cell above. If I move the
first cell, I want it to be equal to the cell above, in it's new location,
not the old one. I thought that there was a referencing mode for this but I
can't find any information on it.
Thanks for any advice.
Dab