T
Té
Act Start Act Finish %Comp Act. Dur. Rem Dur.
Act. Cost Act. Work
CSS Training Manual 8/1/05 NA 4% 2.07d 54.93d "$3,280.00" 48h
Start Book 8/1/05 8/1/05 100% 0d 0d $0.00 0h
Research Phase 8/1/05 NA 25% 2d 6d "$3,280.00" 48h
Interview Subject Matter Expert 8/1/05 8/2/05 100% 2d 0d "$3,280.00" 48h
Investigate the software NA NA 0% 0d 4d $0.00 0h
Search the Web NA NA 0% 0d 2d $0.00 0h
I have switched to tracking view with the task sheet. I eneterd a
completion of 100% for task 3 (interview subject) since I have marked this
task complete my actual duration is now 2.07 days and my remaining durations
is 54.93 days. The task took 2 days to complete. The overall phase consists
of 8 days. Where are these decimals coming from? The computer says actual
duration is calculated by duration x percent complete.
Act. Cost Act. Work
CSS Training Manual 8/1/05 NA 4% 2.07d 54.93d "$3,280.00" 48h
Start Book 8/1/05 8/1/05 100% 0d 0d $0.00 0h
Research Phase 8/1/05 NA 25% 2d 6d "$3,280.00" 48h
Interview Subject Matter Expert 8/1/05 8/2/05 100% 2d 0d "$3,280.00" 48h
Investigate the software NA NA 0% 0d 4d $0.00 0h
Search the Web NA NA 0% 0d 2d $0.00 0h
I have switched to tracking view with the task sheet. I eneterd a
completion of 100% for task 3 (interview subject) since I have marked this
task complete my actual duration is now 2.07 days and my remaining durations
is 54.93 days. The task took 2 days to complete. The overall phase consists
of 8 days. Where are these decimals coming from? The computer says actual
duration is calculated by duration x percent complete.