HELP WITH %COMPLETE!!!!

T

Té

Act Start Act Finish %Comp Act. Dur. Rem Dur.
Act. Cost Act. Work
CSS Training Manual 8/1/05 NA 4% 2.07d 54.93d "$3,280.00" 48h
Start Book 8/1/05 8/1/05 100% 0d 0d $0.00 0h
Research Phase 8/1/05 NA 25% 2d 6d "$3,280.00" 48h
Interview Subject Matter Expert 8/1/05 8/2/05 100% 2d 0d "$3,280.00" 48h
Investigate the software NA NA 0% 0d 4d $0.00 0h
Search the Web NA NA 0% 0d 2d $0.00 0h

I have switched to tracking view with the task sheet. I eneterd a
completion of 100% for task 3 (interview subject) since I have marked this
task complete my actual duration is now 2.07 days and my remaining durations
is 54.93 days. The task took 2 days to complete. The overall phase consists
of 8 days. Where are these decimals coming from? The computer says actual
duration is calculated by duration x percent complete.
 
M

Mike Glen

Hi Té,

Fractions can often be explained by mis-matching of settings. You might
like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top