P
ProjectUser84
I am using MS Project 2002. I have two tasks: Clean Kitchen; Work: 1
hours; Resource: Tim Clean Bathroom; Work: 16 hours; Resource: Tim Bu
MS Project is showing both tasks starting at the same time, with th
critical path of 16 hours. The tasks show Tim using 100% effort and Ti
is scheduled to work only 8 hours a day. So why does the task finish i
16 hours and not the expected 30 hours (16+14)? Without creating fals
dependencies, how do I make sure that Project properly shows 1) that th
tasks must be done sequentially, or 2) that Tim's 8-hour work day mus
be split between these two tasks? In either case, the critical pat
should show that this project will have a 30-hour duration.
Read more
http://www.justanswer.com/questions/2lya2-using-ms-project-2002-two-tasks#ixzz0SmlpLTA
hours; Resource: Tim Clean Bathroom; Work: 16 hours; Resource: Tim Bu
MS Project is showing both tasks starting at the same time, with th
critical path of 16 hours. The tasks show Tim using 100% effort and Ti
is scheduled to work only 8 hours a day. So why does the task finish i
16 hours and not the expected 30 hours (16+14)? Without creating fals
dependencies, how do I make sure that Project properly shows 1) that th
tasks must be done sequentially, or 2) that Tim's 8-hour work day mus
be split between these two tasks? In either case, the critical pat
should show that this project will have a 30-hour duration.
Read more
http://www.justanswer.com/questions/2lya2-using-ms-project-2002-two-tasks#ixzz0SmlpLTA